
The biggest operation by far is Phase II of the Madison Valley Stormwater Project, which will be getting underway in July. As previously reported here, a pipeline will be constructed to collect stormwater from the northwest section of Madison Valley and channel it to a newly built mostly-below-ground tank located near the ball field in Washington Park. Bryan Nicholson, the project engineer for Phase II at Seattle Public Utilities, tells me that the project will begin next month with some excavation work related to the replacement of a major water main along Madison Street. No water outages are anticipated for Madison Park residents.
By late July we may see some traffic impact resulting from site work on the Washington Park end of the project. An access road will be created off of the north side of Madison Street, with the road’s entrance situated about halfway between the Madison Lofts Condos (2914 E. Madison) and Lake Washington Boulevard. On the site map above, which shows the landscape plan for the completed project, the “pedestrian entry” is also the location of the construction access road.
The pipeline itself will be an underground affair, with the impact of above-ground construction expected to be fairly limited—unless you happen to live in Madison Valley near the site of the staging area (shown in blue on the map below) or near one of the eight pipeline shafts. Construction of the pipeline will begin at the Washington Park end (shaft 8) in August.
.jpg)
Phase II has an 18-month construction schedule, culminating in the fall of 2011. Nicholson reports that traffic along Madison Street should seldom need to be stopped during construction as there is enough width to allow two-way flow, even when construction is occurring along the side. For more information on the Madison Valley Stormwater Project, visit the City’s official site. Questions can be directed to a 24-hour hotline: (206) 455-5345.
According to Seattle City Light spokesperson Mark VanOss, work will be scheduled to minimize disruption to rush-hour traffic on the Boulevard. This summer’s phase of the project will concentrate on 29 lights from the Broadmoor entrance at E. Foster Island Road to a point 500 feet south of the pedestrian bridge over Lake Washington Boulevard. These replacements should be completed by the end of October, with the work on the remaining 42 lights to begin sometime next year.
[Stormwater graphics courtesy of Seattle Public Utilities.]
I think the photo you showed of the street light also shows another reason for re-routing the construction trucks away from the Arboretum. Behind the street light is the old brick bridge located at the north end of the Arboretum. We have all the seen the remains of buses, rental trucks and RV's that couldn't make it underneath the arched entry. I doubt if the construction trucks can make it through either.
ReplyDelete